Which of the following best completes the passage below?

When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because _____________.

(A) the project may have failed for reasons that the original manager could not have foreseen
(B) organizations tend to reward managers who can overcome problems
(C) managerial decisions to terminate a project should depend on the likelihood of the project's eventual success
(D) the original managers were not necessarily able to overcome problems caused by external events over which they had no control
(E) the new managers have no need to justify the earlier decision to maintain the project

正解E。

なぜ正解がEなのか分かりません。
どなたか解説いただけたらと思います。
よろしくお願いします。